Implementing last planner in the context of social housing retrofit

Sergio Kemmer, Clarissa Biotto, Fernanda Chaves, Lauri Koskela, Patricia Tzortzopoulos

Research output: Chapter in Book/Report/Conference proceedingConference contributionpeer-review

4 Citations (Scopus)

Abstract

The paper aims to investigate the implementation issues and benefits of utilising the Last Planner and 4D modelling in the context of retrofit of social housing. It presents initial results of an on-going research project carried out in Northern Ireland, which focuses on the retrofit of solid wall homes. The research project involves the proposal of a process in which BIM is used to evaluate what-if scenarios for the retrofit of social housing with a focus on reducing user's disruption throughout the construction process. Both 4D and the Last Planner are used to ensure the retrofit works with the minimum disruption. A case study on the retrofit of a set of houses was carried out, which is part of a bigger research project entitled S-IMPLER. Data was collected via semi-structured interviews, participant observation in planning meetings, site visits and documental analysis. The study sheds light on a particular type of project that has not been well explored by the lean community, i.e. retrofits. It is argued that the results can be applicable to support the retrofit of a number of solid wall homes throughout the UK.

Original languageEnglish
Title of host publicationIGLC 2016 - 24th Annual Conference of the International Group for Lean Construction
PublisherNational Pingtung University of Science and Technology
Pages83-92
Number of pages10
Publication statusPublished - 2016
Event24th Annual Conference of the International Group for Lean Construction: On the Brink of Lean Revolution - Boston, United States
Duration: 18 Jul 201624 Jul 2016
Conference number: 24
http://iglc2016.com/wp-content/uploads/2017/05/2016-07-16-IGLC-Conference-Program.pdf (Link to Conference Programme)

Conference

Conference24th Annual Conference of the International Group for Lean Construction
Abbreviated titleIGLC 2016
CountryUnited States
CityBoston
Period18/07/1624/07/16
Internet address

Fingerprint

Dive into the research topics of 'Implementing last planner in the context of social housing retrofit'. Together they form a unique fingerprint.

Cite this