Abstract
Schedule delay and cost overrun are the two major challenges for the successful project delivery in construction. It has been reported that significant delays in construction projects are caused by rework and there are several reasons for rework. A framework has been proposed to assess the delay due to two primary reasons for rework, (i.e. design changes and non-conformances), using Multiple Domain Matrix (MDM), a matrix-based technique. This methodology would help the project planners to create an as-adjusted schedule that is more appropriate compared to as-planned or as-built schedules. Further, it is possible to arrive at a meaningful estimate of activity buffer time in order to account for delays due to rework. Eventually, this would lead to successfully implement one of the key principles of lean, namely, elimination of time-related “waste” that is due to defect and/or delay.
Original language | English |
---|---|
Title of host publication | Proceedings of the 26th Annual Conference of the International Group for Lean Construction |
Editors | Vicente A Gonzalez |
Publisher | The International Group for Lean Construction |
Pages | 1344-1353 |
Number of pages | 10 |
Volume | 2 |
ISBN (Print) | 9789380689296 |
DOIs | |
Publication status | Published - 16 Jul 2018 |
Externally published | Yes |
Event | 26th Annual Conference of the International Group for Lean Construction: Evolving Lean Construction - Towards Mature Production Across Cultures and Frontiers - Chennai, India Duration: 16 Jul 2018 → 22 Jul 2018 Conference number: 26 http://iglc2018.com/ (Link to Conference Website) http://iglc2018.com/downloads/IGLC2018-Proceedings-Vol1_Vol2.pdf |
Publication series
Name | Proceedings of the International Group for Lean Construction |
---|---|
Publisher | International Group for Lean Construction (IGLC) |
ISSN (Print) | 2309-0979 |
Conference
Conference | 26th Annual Conference of the International Group for Lean Construction |
---|---|
Abbreviated title | IGLC 2018 |
Country/Territory | India |
City | Chennai |
Period | 16/07/18 → 22/07/18 |
Internet address |
|